2010 I-355  Reconstruction Project

 
 

The I-355 project consisted of a 3 lift overlay of the existing concrete pavement on I-355 between Butterfield and Army Trail Roads with additional repairs to bridges and noise walls.  The overlay sequence was an initial ” lift of Polymerized Leveling Binder IL 4.75 followed by a 1.75” lift of Stone Matrix Asphalt Binder and a 1.75” list of Stone Matrix Asphalt Friction Surface Course.  The paving work was done between 3:00Pm and 12:00AM to minimize traffic delay and to allow the asphalt plant to be dedicated to this project.  A total of 130,000 tons of asphalt were placed on this project.  We are pleased that this project received the Illinois State Toll Highway Authority’s award as Best Pavement of 2010.

 