Award Winning Projects

We have several projects which demonstrate our workmanship . A number have won awards. Here are a few notable ones.

NAPA

National Asphalt Pavement Association 

2023 NAPA Chair Christian Zimmermann. “Earning the Quality in Construction Award demonstrates that Geneva Construction has met or exceeded these rigorous standards.”

2023 Quality in Construction Award 

Project: North Aurora Road 

Geneva Construction won the award for its work on North Aurora Rd. in Naperville, Ill. The company rebuilt the road with asphalt binder and surface courses, incorporating fractionated reclaimed asphalt pavement (FRAP) into the mixes. This is a sustainable paving practice that conserves virgin materials and reduces greenhouse gas emissions. Using echelon pavers to minimize longitudinal joints, Geneva Construction produced a smooth, high-quality asphalt road.

Sustainability Paving

Echelon Paving Technique

Geneva Construction Company paved this project using the Echelon paving technique. Echelon paving is when you pave with two asphalt pavers side by side to minimize longitudinal joints. Geneva Construction Company produced a smooth, high-quality asphalt road. We paved the road with incorporating fractionated reclaimed asphalt pavement (FRAP) into the mix design from Superior Asphalt Materials, LLC This is a sustainable paving practice that conserves virgin materials and reduces greenhouse gas emissions.

2018 Rehab of I-88
Joint Project with Curran Construction Co.

Contractor of the Year
11 miles of HMA paving from Aurora, Illinois to Dekalb county line.   A total of 131,461 TONS of HMA materials, such as Polymerized Level Binder, Stone Matrix Binder and Stone Matrix Surface were produced and shipped from our own asphalt plant in North Aurora, Illinois just for this project.

2016 US 30 at Dugan Road, Sugar Grove

Contractor of the Year
A total of 22,175 TONS of HMA Surface and Binder materials were produced and shipped at our asphalt plant in North Aurora, Illinois for this project. 

2010 Rehab of I-355 

Contractor of the Year
8.1 miles of concrete (PCC) overlay from Butterfield Rd to Army Trail Rd. HMA paving on shoulders. All work performed at night. 
A total of 95,485 TONS of HMA Binder and Surface materials were produced and shipped from our own asphalt plant in North Aurora, Illinois just for this project.




AU New Parking Lots